Craig Thompson
Approved1641 CLUB RD CHARLOTTE NC 28205Tracked since Apr 23, 2026
This file is open for you, every name on it. The next one asks for an email.Create a free accountno card · 3 files, then 1 a week · Radar every morning · Charlotte
Specifications
- Status
- Approved
- Data as of
- Apr 24, 2026
From the permits
Permit2026-04-24
Alteration · Single family$0.0M
Concrete
owner Thompson Craig A
Change History
- Project first trackedApr 24, 2026·public record
Public Record
PermitRES-ALT-26-001294$4,202Apr 24, 2026
Construction / Alteration: (3) CMU Pier-Install new CMU, 8"x8"x16" pier. With new footing to be sized at 20"x20"x10" deep. Pier will be solid topped. Per code or engineer specifications. Needs three cmu piers. Locations and footing size per engineer report. (1) Bracing-Needs bracing. Brace and straighten existing drop girder per engineer specifications. (1) Rebuild CMU Pier-Remove loose portion of existing pier and rebuild to code or engineer specifications.
Everything the source published · 20 fields ▸▾
- Owner
- THOMPSON CRAIG A
- Owner mailing address
- 1641 CLUB RD,CHARLOTTE,NC,28205
- Zip code
- 28205
- Issue date
- Apr 24, 2026
- Description
- (3) CMU Pier-Install new CMU, 8"x8"x16" pier. With new footing to be sized at 20"x20"x10" deep. Pier will be solid topped. Per code or engineer specifications. Needs three cmu piers. Locations and footing size per engineer report. (1) Bracing-Needs bracing. Brace and straighten existing drop girder per engineer specifications. (1) Rebuild CMU Pier-Remove loose portion of existing pier and rebuil…
- Project name
- Craig Thompson
- Type of work
- Alteration
- Permit number
- RES-ALT-26-001294
- Permit status
- Closed - Complete
- Completion date
- May 14, 2026
- Permit fee type
- Construction
- Project address
- 1641 CLUB RD CHARLOTTE NC 28205
- Tax jurisdiction
- CHARLOTTE
- Total square feet
- 0
- Cama parcel number
- 09508347
- Heated square feet
- 0
- Description of work
- (3) CMU Pier-Install new CMU, 8"x8"x16" pier. With new footing to be sized at 20"x20"x10" deep. Pier will be solid topped. Per code or engineer specifications. Needs three cmu piers. Locations and footing size per engineer report. (1) Bracing-Needs bracing. Brace and straighten existing drop girder per engineer specifications. (1) Rebuild CMU Pier-Remove loose portion of existing pier and rebuil…
- Usdc code and description
- 434 - RES DWELLING (ADD, ALTERATION, REPAIR, REPLACE)
- Building construction cost system
- 0
- Building construction cost customer
- $4,202