Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
Site work
Site work permit: R&D Realty LLC, under RP-2025-010359 · Site / Utility Permit for RP-2025-010359 · 1 permit
Mar 4, 2026
Plumbing
Plumbing permit: THOMAS UHL, under RP-2025-010359 · Plumbing Permit (Water Distribution) for combo RP-2025-010359 · 4 permits
Dec 28, 2025 to Mar 4, 2026
HVAC
Mechanical permit: Oris-Hvac Inc, under RP-2025-010359 · Mechanical / Fuel Gas Permit for combo RP-2025-010359 · 2 permits
Dec 28, 2025 to Mar 4, 2026
Fire protection & life safety
Fire suppression permit: DC MECHANICAL II LLC, under RP-2025-010359 · FOR THE INSTALLATION OF A FIRE SUPPRESSION SYSTEM IN ACCORDANCE WITN NFPA 13D, WITH A ONE-INCH COMBINED FIRE SERVICE LINE, AS PER APPROVED PLANS. ALL WORK SHALL BE PERFORMED BY A FIRE SUPPRESSION CONTRACTOR LICENSED BY THE CITY OF PHILADELPHIA. · 2 permits
Dec 28, 2025 to Jul 17, 2026
Other trade
Residential new construction: FOR THE ERECTION OF AN ATTACHED STRUCTURE FOR USE AS A TWO (2) -FAMILY HOUSEHOLD LIVING. SHEETING AND SHORING AS PRESCRIBED IN GEOTECH REPORT. (UNDERPINNING NOT A PART OF THIS PERMIT). SEPARATE PERMITS REQUIRED FOR SPRINKLER (NFPA 13D) WORK. ENERGY CODE COMPLIANCE IN ACCORDANCE WITH 2018 IECC. PRIOR TO ISSUANCE OF C/O SUBMITTAL OF AIR BARRIER CHECKLIST AND ENVELOPE TESTING CERTIFICATE IS REQUIRED. BOTH TO BE COMPLETED BY AN APPROVED PARTY. · 1 permit
Dec 28, 2025
Other trade
Residential new construction: FOR THE ERECTION OF AN ATTACHED STRUCTURE FOR USE AS A TWO (2) -FAMILY HOUSEHOLD LIVING. SHEETING AND SHORING AS PRESCRIBED IN GEOTECH REPORT. (UNDERPINNING NOT A PART OF THIS PERMIT). SEPARATE PERMITS REQUIRED FOR SPRINKLER (NFPA 13D) WORK. ENERGY CODE COMPLIANCE IN ACCORDANCE WITH 2018 IECC. PRIOR TO ISSUANCE OF C/O SUBMITTAL OF AIR BARRIER CHECKLIST AND ENVELOPE TESTING CERTIFICATE IS REQUIRED. BOTH TO BE COMPLETED BY AN APPROVED PARTY. · 1 permit
Dec 28, 2025
Other trade
Residential new construction: FOR THE ERECTION OF AN ATTACHED STRUCTURE FOR USE AS A TWO (2) -FAMILY HOUSEHOLD LIVING. SHEETING AND SHORING AS PRESCRIBED IN GEOTECH REPORT. (UNDERPINNING NOT A PART OF THIS PERMIT). SEPARATE PERMITS REQUIRED FOR SPRINKLER (NFPA 13D) WORK. ENERGY CODE COMPLIANCE IN ACCORDANCE WITH 2018 IECC. PRIOR TO ISSUANCE OF C/O SUBMITTAL OF AIR BARRIER CHECKLIST AND ENVELOPE TESTING CERTIFICATE IS REQUIRED. BOTH TO BE COMPLETED BY AN APPROVED PARTY. · 1 permit
Dec 28, 2025
Other trade
Residential new construction: FOR THE ERECTION OF AN ATTACHED STRUCTURE FOR USE AS A TWO (2) -FAMILY HOUSEHOLD LIVING. SHEETING AND SHORING AS PRESCRIBED IN GEOTECH REPORT. (UNDERPINNING NOT A PART OF THIS PERMIT). SEPARATE PERMITS REQUIRED FOR SPRINKLER (NFPA 13D) WORK. ENERGY CODE COMPLIANCE IN ACCORDANCE WITH 2018 IECC. PRIOR TO ISSUANCE OF C/O SUBMITTAL OF AIR BARRIER CHECKLIST AND ENVELOPE TESTING CERTIFICATE IS REQUIRED. BOTH TO BE COMPLETED BY AN APPROVED PARTY. · 1 permit