The subs and their phones are locked. Pro shows every one, $27 a month.
Trades on this job
Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
Plumbing
Plumbing permit: J Aiken Evans, under CP-2025-000325 · Install 1 three compartment sink, 1 hand sink, 1 mop sink and 3 floor sinks. All work to be done according to the 2018 PPC and per approved plans. · 1 permit
Jan 5, 2026
Electrical
Electrical permit: HARUN WILSON, under CP-2025-000325 · Legalizing work performed by others. Added electrical outlets throughout the kitchen area and installed new outlets and recessed lighting in the front counter areas as per 2017 NEC. Replaced the outdated and non-functional fire alarm system as per 2016 NFPA 72. · 1 permit
Jan 6, 2026
Electrical
Electrical permit: Maurice Samuels, under CP-2025-004780 · Removal of 5 unit meter bank to convert to a single 200 amp metering with 200 amp panel existing risers to be connected to new 200 amp panel grounding as per print · 3 permits
Feb 20, 2026 to Sep 22, 2026
Plumbing
Plumbing permit: KENNETH DIXON, under CP-2025-004780 · Swap out existing 5 bathrooms fixtures 5 W/C, 5 Lavatory’s and kitchen Sink, Cap off the other 4 drain lines that not being used. · 2 permits
Feb 20, 2026 to Jul 27, 2026
Fire protection & life safety
Fire suppression permit: ELITE FIRE PROTECTION CORP, under CP-2025-004780 · FOR THE INSTALLATION OF AN NFPA 13R SYSTEM THROUGHOUT 2ND TO 4TH FLOOR SERVICED BY A TWO (2) INCH FIRE SERVICE LINE WITH 2-INCH WILKINS 950XLT2 BACKFLOW PREVENTER ASSEMBLY. FIRE SYSTEM TO INCLUDE THE INSTALLATION OF ONE STANDPIPE IN EXIT STAIRWAY. ALL WORK TO BE DONE PER APPROVED PLANS. IF FIELD CONDITIONS VARY CONTACT DESIGN ENGINEER PRIOR TO THE START OF ANY WORK. IF FIELD CONDITIONS VARY CONTACT DESIGN ENGINEER PRIOR · 2 permits