The subs and their phones are locked. Pro shows every one, $27 a month.
Trades on this job
Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
HVAC
Mechanical permit: OREILLY EDWARD B & ASSOC INC, under CP-2025-005290 · FOR THE INSTALLATION OF APPLIANCES WITH ASSOCIATED DUCTWORK. APPLIANCES TO BE INSTALLED IN ACCORDANCE WITH MANUFACTURER'S SPECIFICATIONS. ALL WORK TO BE DONE PER APPROVED PLANS. IF FIELD CONDITIONS VARY CONTACT DESIGN ENGINEER PRIOR TO THE START OF ANY WORK. SEPARATE PERMITS REQUIRED FOR ALL OTHER WORK. *NO REGISTERS, DIFFUSERS ON THIS PERMIT. · 2 permits
Jan 8, 2026 to Jun 12, 2026
Electrical
Electrical permit: SHELLY ELECTRIC CO INC, under CP-2025-005290 · Install fire fire pump service and related equipment. (see sheet for relocated equipment ) ALL WORK IS TO BE DONE ACCORDING TO APPROVED DRAWINGS-2017 NEC. · 2 permits
Jan 8, 2026 to Oct 7, 2026
Fire protection & life safety
Fire suppression permit: Oliver Sprinkler Co., Inc, under CP-2025-005290 · FOR ALTERATIONS TO AN EXISTING AUTOMATIC SPRINKLER SYSTEM TO INCLUDE THE INSTALLATION OF NEW PRIVATE YARD FIRE HYDRANT, EIGHT (8) INCH FIRE SERVICE LINE, EIGHT (8) INCH BACKFLOW PREVENTER, AND FIRE PUMP. ALL WORK TO BE DONE PER APPROVED PLANS AND IN ACCORDANCE WITH NFPA 13 AND NFPA 20. SEPARATE PERMITS TO BE OBTAINED FOR ALL OTHER WORK. SEE CP-2025-005290 FOR ASSOCIATED BUILDING PERMIT. · 2 permits