The subs and their phones are locked. Pro shows every one, $27 a month.
Trades on this job
Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
Electrical
Electrical permit: REDLINE ELECTRIC, under CP-2025-004363 · AMEND PERMIRT 2/2/2026 - Extend Circuits' From Existing Panel to Relocation Of Devices INTERIOR REWIRE OF APARTMENT/CONDO WALLS FISHING METHOD ONLY · 1 permit
Nov 30, 2025
Plumbing
Plumbing permit: Adelphia Plumbing and Heating Services Inc, under CP-2025-004363 · Kitchen, laundry, and bathroom modifications. 10 FIXTURES · 1 permit
Dec 2, 2025
Electrical
Electrical permit: marquis henderson, under CP-2026-001966 · Rewiring an apartment unit inside of an apartment building. Installing new non-metallic Romex cable for lighting receptacles smoke detectors appliances switches and throughout the dwelling. All work to be perform according to the 2017 NEC and per approved executed contract. · 8 permits
Dec 16, 2025 to Jul 24, 2026
Fire protection & life safety
Fire suppression permit: A & S SPRINKLER CO INC, under CP-2025-006471 · EZ PERMIT SPRINKLER RELOCATION (NFPA 13)- For the relocation of sprinkler heads as per attached standards. Deviations from these standards require submission of construction and site plans. RELOCATE (13) SPRINKLER HEADS, PER NFPA 13 · 4 permits
Dec 16, 2025 to Mar 17, 2026
Fire protection & life safety
Fire suppression permit: ONEIDA FIRE PROTECTION INC, under CP-2026-001966 · EZ PERMIT SPRINKLER RELOCATION (NFPA 13)- For the relocation of sprinkler heads as per attached standards. Deviations from these standards require submission of construction and site plans. Relocating 15 existing sprinkler heads, for the combining of units 5E and 5F into (1) dwelling unit, per NFPA 13 · 4 permits