The subs and their phones are locked. Pro shows every one, $27 a month.
Trades on this job
Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
Plumbing
Plumbing permit: PLUMETRIX INC, under CP-2025-005664 · new plumbing system for triplex including 5 tub/shower 3 kitchen sinks 3 water heaters 3 washer boxes 5 lavatories 3 laundry sinks 5 water closets · 2 permits
Jan 7, 2026 to Mar 23, 2026
HVAC
Mechanical permit: NAZAR HOME CONSTRUCTION INC, under CP-2025-005664 · **2021 IMC REVIEW** FOR THE INSTALLATION OF REGISTERS, DIFFUSERS, AND APPLIANCES WITH ASSOCIATED DUCTWORK. APPLIANCES TO BE INSTALLED IN ACCORDANCE WITH THE MANUFACTURER’S SPECIFICATIONS. ALL WORK TO BE DONE PER APPROVED PLANS. IF FIELD CONDITIONS VARY CONTACT DESIGN ENGINEER PRIOR TO THE START OF ANY WORK. SEPARATE PERMITS REQUIRED FOR ALL OTHER WORK. · 2 permits
Jan 7, 2026 to May 7, 2026
Electrical
Electrical permit: EAGLE ELECTRICAL CONSTRUCTION CO INC, under CP-2025-005664 · Install 300 amp service equipment and grounding. Wiring throughout the building. Install light fixtures, outlets, switches, smoke/CO alarms, emergency lights, and exit signs as per 2017 NEC. Install fire alarm system as per 2016 NFPA 72. · 2 permits
Jan 7, 2026 to May 18, 2026
Fire protection & life safety
Fire suppression permit: Michael J Mccullough jr, under CP-2025-005664 · FOR THE INSTALLATION OF A 2-INCH FIRE SERVICE LINE FOR AN AUTOMATIC FIRE SUPPRESSION SPRINKLER SYSTEM WITH A 2 INCH WILKINS 950XLT2 BACKFLOW PREVENTION ASSEMBLY IN ACCORDANCE WITH NFPA 13R. ALL WORK SHALL BE DONE IN ACCORDANCE WITH APPROVED PLANS/HYDRAULIC CALCULATIONS. · 2 permits
Jan 7, 2026 to Feb 5, 2026
Plumbing
Plumbing permit: THOMAS UHL, under CP-2025-005664 · INSTALL SANITARY AND STORM CTs, FAIs, MD & 1.5” WATER DISTRIBUTION PIPE. · 2 permits
Jan 7, 2026 to Mar 3, 2026
Other trade
Multifamily new construction: NEW CONSTRUCTION OF A THREE (3) STORY & MEZZANINE, THREE (3) FAMILY DWELLING WITH ROOF DECK AND ROOF DECK ACCESS STRUCTURE TO INCLUDE UNDERPINNING AS PER APPROVED PLANS. BUILDING TO BE FULLY SPRINKLERED PER NFPA 13R. SEPARATE PERMITS REQUIRED FOR MEP & FIRE SUPPRESSION WORK. *2018 IBC REVIEW *NO EXCAVATION GREATER THAN 5FT.* · 1 permit
Jan 7, 2026
Other trade
Multifamily new construction: NEW CONSTRUCTION OF A THREE (3) STORY & MEZZANINE, THREE (3) FAMILY DWELLING WITH ROOF DECK AND ROOF DECK ACCESS STRUCTURE TO INCLUDE UNDERPINNING AS PER APPROVED PLANS. BUILDING TO BE FULLY SPRINKLERED PER NFPA 13R. SEPARATE PERMITS REQUIRED FOR MEP & FIRE SUPPRESSION WORK. *2018 IBC REVIEW *NO EXCAVATION GREATER THAN 5FT.* · 1 permit