The subs and their phones are locked. Pro shows every one, $27 a month.
Trades on this job
Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
Site work
Site work permit: GROSSO CONCRETE LLC, under RP-2025-012265 · Site / Utility Permit for RP-2025-012265 · 2 permits
Mar 5, 2026 to Mar 19, 2026
Electrical
Electrical permit: Baldwin Electrical Construction LLc, under RP-2025-012265 · Electrical Permit for combo RP-2025-012265 · 2 permits
Mar 5, 2026 to Oct 21, 2026
Plumbing
Plumbing permit: AK SCORPION INC, under RP-2025-012265 · Plumbing Permit (Exterior Building Drainage) for combo RP-2025-012265 · 4 permits
Mar 5, 2026 to May 5, 2026
Fire protection & life safety
Fire suppression permit: METROPOLITAN FIRE PROTECTION, under RP-2025-012265 · FOR THE INSTALLATION OF AN AUTOMATIC FIRE SUPPRESSION SYSTEM IN ACCORDANCE WITH NFPA 13D THROUGHOUT THREE STORY BUILDING TO INCLUDE 1-INCH COMBINED WATER SERVICE LINE AS PER APPROVED PLANS. ALL WORK SHALL BE DONE IN ACCORDANCE WITH APPROVED PLANS/HYDRAULIC CALCULATIONS. IF FIELD CONDITIONS VARY CONTACT DESIGN ENGINEER PRIOR TO THE START OF ANY WORK. · 2 permits