The subs and their phones are locked. Pro shows every one, $27 a month.
Trades on this job
Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
Site work
Site work, sitework with onsite utility services: FOR SITEWORK AS PER APPROVED PLANS. *NO EXCAVATION ON THIS PERMIT* · 2 permits
May 28, 2026 to Aug 5, 2026
Demolition
Demolition permit: GEPPERT BROS INC, under CP-2024-005400 · FOR THE COMPLETE DEMOLITION OFEXISTING MASONRY AND WOOD ONE-STORY STRUCTURE BY MECHANICAL METHODS. ALL PERMITTED DEMOLITION ACTIVITY TO BE IN ACCORDANCE WITH APPROVED SITE SAFETY DEMOLITION PLAN & SUCH PLAN TO BE MAINTAINED ON SITE AT ALL TIMES IN ACCORDANCE WITH PHILADELPHIA ADMINISTRATIVE CODE. COMPLETE SIDEWALK CLOSURE REQUIRED AS REFLECTED ON APPROVED SITE PLAN AND IN ACCORDANCE WITH SECTION 3306 OF THE IBC. SEPARATE STREET CLOSURE · 1 permit
Jun 16, 2026
Site work
Site work, sitework with onsite utility services: SITEWORK ASSOCIATED WITH UTILITY INSTALLATION FOR NEW MAINTENANCE BUILDINGS (SEE PERMITS CP-2024-004894 & CP-2024-005400) AS PER APPROVED PLANS. *2018 IBC REVIEW* **SEPARATE PERMITS REQUIRED FOR PLUMBING WORK** · 1 permit
Jul 24, 2026
Fire protection & life safety
Fire suppression permit: Precision Sprinkler Services, Inc, under CP-2024-004894 · FOR INSTALLATION OF A 6-INCH FIRE SERVICE LINE, 8-INCH BACKFLOW PREVENTER AT METER PIT, AND FIRE SPRINKLER SYSTEM IN ACCORDANCE WITH APPROVED PLANS, HYDRAULIC CALCULATIONS AND NFPA 13. · 2 permits
Jun 29, 2026 to Sep 28, 2026
Plumbing
Plumbing permit: FIVE STAR INCORPORATED, under CP-2024-004894 · NEW CONSTRUCTION OF A ONE-STORY DETACHED STRUCTURE (BUILDING 'A') FOR USE AS A MAINTENANCE AND STORAGE FACILITY SERVING AN EXISTING ACTIVE RECREATIONAL FACILITY (GOLF COURSE) AS PER APPROVED PLANS. · 4 permits
Jun 29, 2026 to Sep 15, 2026
HVAC
Mechanical permit: WEST CHESTER MECHANICAL CONTRACTORS INC, under CP-2024-004894 · INSTALLATION OF HVAC SYSTEM FOR MAINTENANCE AND STORAGE FACILITY (BUILDING 'A') SERVING AN EXISTING ACTIVE RECREATIONAL FACILITY (GOLF COURSE) AS PER APPROVED PLANS. · 4 permits
Jun 29, 2026 to Sep 16, 2026
Electrical
Electrical permit: FOX CHASE ELECTRICAL INC, under CP-2024-004894 · Temp Service hookup to job trailer with PECO temporary meter. · 2 permits