The subs and their phones are locked. Pro shows every one, $27 a month.
Trades on this job
Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
Electrical
Electrical permit: B.H. HOLDINGS CORP ( Emergency Response Associates), under CP-2026-001147 · Furnish and install a fire alarm system for the office fit-out on the third and fourth floors. Work includes installation of initiating devices, notification appliances, wiring, terminations, and system components required for each floor. Provide interconnection and wiring from the third and fourth floor systems to the existing main fire alarm control panel located on the first floor. All work shall be · 2 permits
Mar 13, 2026 to Apr 10, 2026
Fire protection & life safety
Fire suppression permit: ONEIDA FIRE PROTECTION INC, under CP-2026-001147 · EZ PERMIT SPRINKLER RELOCATION (NFPA 13)- For the relocation of sprinkler heads as per attached standards. Deviations from these standards require submission of construction and site plans. Relocate 50 existing sprinkler heads to ensure the safety of the building, per NFPA 13 · 2 permits
Mar 13, 2026 to Mar 20, 2026
Electrical
Electrical permit: A&I Electrical Construction, LLC, under CP-2026-001147 · Electrical renovations to the 3rd and 4th floor of an apartment building. Turning the two floors into offices with all lighting ,receptacles and data. ALL WORK IS TO BE DONE ACCORDING TO APPROVED DRAWINGS-2017 NEC. **NO FIRE ALARM ON THIS PERMIT** · 2 permits
Mar 13, 2026 to Jun 1, 2026
Plumbing
Plumbing permit: OK PLUMBING LLC, under CP-2026-001147 · Replace fixtures: 8 lavatories, 15 toilet/urinals. **WITHOUT PIPING** · 2 permits
Mar 13, 2026 to Mar 17, 2026
Other trade
Commercial tenant fit-out: FOR LEVEL II ALTERATIONS FOR FITOUT OF 3RD & 4TH FLOORS TO INCLUDE NEW PARTITIONS, FIXTURES, FURNISHINGS, FINISHES AS PER APPROVED PLANS. SEPARATE PERMITS REQUIRED FOR MEP AND FIRE SUPRRESSION WORK. *2018 IEBC* · 1 permit
Mar 13, 2026
Other trade
Commercial tenant fit-out: FOR LEVEL II ALTERATIONS FOR FITOUT OF 3RD & 4TH FLOORS TO INCLUDE NEW PARTITIONS, FIXTURES, FURNISHINGS, FINISHES AS PER APPROVED PLANS. SEPARATE PERMITS REQUIRED FOR MEP AND FIRE SUPRRESSION WORK. *2018 IEBC* · 1 permit
Mar 13, 2026
Other trade
Commercial tenant fit-out: FOR LEVEL II ALTERATIONS FOR FITOUT OF 3RD & 4TH FLOORS TO INCLUDE NEW PARTITIONS, FIXTURES, FURNISHINGS, FINISHES AS PER APPROVED PLANS. SEPARATE PERMITS REQUIRED FOR MEP AND FIRE SUPRRESSION WORK. *2018 IEBC* · 1 permit
Mar 13, 2026
Other trade
Commercial tenant fit-out: FOR LEVEL II ALTERATIONS FOR FITOUT OF 3RD & 4TH FLOORS TO INCLUDE NEW PARTITIONS, FIXTURES, FURNISHINGS, FINISHES AS PER APPROVED PLANS. SEPARATE PERMITS REQUIRED FOR MEP AND FIRE SUPRRESSION WORK. *2018 IEBC* · 1 permit