The subs and their phones are locked. Pro shows every one, $27 a month.
Trades on this job
Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
Electrical
Electrical permit: GERALD D KAEWELL, under CP-2025-006263 · Install 5 dedicated 120 volt lines for commercial use. Install 3 new EXIT signs, 3 lighting fixtures. Replace two existing Horn/Strobes with new. All wiring is to be done using the fishing method. No open walls or new construction **FISHING ONLY · 2 permits
Apr 20, 2026 to Apr 27, 2026
HVAC
Mechanical permit: Reliable Fire & Mechanical, Inc, under CP-2025-006263 · FOR THE INSTALLATION OF A TYPE 1 COMMERCIAL KITCHEN HOOD (16'-0") AND ASSOCIATED DUCTWORK, FANS AS PER APPROVED PLANS. SEPARATE PERMITS REQUIRED FOR ELECTRICAL AND FIRE SUPPRESSION WORK. **IMC 2018** · 2 permits
Apr 20, 2026 to Jun 26, 2026
Fire protection & life safety
Fire suppression permit: Reliable Fire & Mechanical, Inc, under CP-2025-006263 · EZ KITCHEN FIRE SUPPRESSION- For the installation of New Wet Chemical Kitchen Fire Suppression System as per attached standard. Deviations from these standards require submission of construction and site plans. To install a wet chemical fire suppression system for a 16'-0" hood system. · 1 permit