The subs and their phones are locked. Pro shows every one, $27 a month.
Trades on this job
Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
Electrical
Commercial change of use: FOR CHANGE OF USE (NO CHANGE OF OCCUPANCY CLASSIFICATION) AND LEVEL II ALTERATIONS TO INCLUDE EXTERIOR WALL OPENINGS, PARTITIONS, DOORS, FIXTURES, FINISHES AS PER APPROVED PLANS. SEPARATE PERMITS REQUIRED FOR ANY MEP WORK. · 2 permits
Nov 13, 2025 to Feb 17, 2026
Plumbing
Plumbing permit: JOSEPH MORETTI, under CP-2025-006323 · REPLACE 5 FIXTURES 1 full bath, 1 urinal, injection pump. · 2 permits
Feb 17, 2026 to Feb 24, 2026
Electrical
Electrical permit: EAST COAST ELECTRICAL SERVICES INC, under CP-2025-006323 · AMEND 04/07/2026 Interior wiring Replacement of existing lights, switches, exit signs and outlets. 120volts/240volts. NO WIRING THIS PERMIT · 2 permits
Feb 17, 2026 to Mar 28, 2026
Plumbing
Plumbing permit: DANIELS CONTRACTING OF PHILADELPHIA, under CP-2025-006323 · REPLACE 1" BACKFLOW DEVICE. · 2 permits
Feb 17, 2026 to Apr 24, 2026
HVAC
Mechanical permit: Shay Argaman, under CP-2025-006323 · FOR THE INSTALLATION OF REGISTERS, DIFFUSERS, AND APPLIANCES WITH ASSOCIATED DUCTWORK. APPLIANCES TO BE INSTALLED IN ACCORDANCE WITH THE MANUFACTURER’S SPECIFICATIONS. FOR USE AS PREVIOUSLY APPROVED. ALL WORK TO BE DONE PER APPROVED PLANS. IF FIELD CONDITIONS VARY CONTACT DESIGN ENGINEER PRIOR TO THE START OF ANY WORK. SEPARATE PERMITS TO BE OBTAINED FOR ALL OTHER WORK. · 2 permits