The subs and their phones are locked. Pro shows every one, $27 a month.
Trades on this job
Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
Demolition
Demolition: FOR THE COMPLETE DEMOLITION OF ONE EXISTING TWO (2) STORY BUILDING BY HAND HELD DEVICES AND MECHANICAL DEMOLITION. ALL PERMITTED DEMOLITION ACTIVITY TO BE IN ACCORDANCE WITH APPROVED SITE SAFETY DEMOLITION PLAN & SUCH PLAN TO BE MAINTAINED ON SITE AT ALL TIMES IN ACCORDANCE WITH PHILADELPHIA ADMINISTRATIVE CODE.ANY DEVIATION WILL REQUIRE AN AMENDED BUILDING PERMIT. PEDESTRIAN PROTECTION TO BE IN PLACE PRIOR TO START OF WORK AND TO BE MAINTAINED DURING ALL DEMOLITION ACTIVITIES. * A C · 1 permit
Jul 20, 2026
Site work
Site work, excavation: EXCAVATION WORK ASSOCIATED WITH RESIDENTIAL DEVELOPMENT AND UNDERGROUND PARKING TO INCLUDE SHEETING & SHORING AND UNDERPINNING WORK AS PER APPROVED PLANS. UNDERPINNING TO BE MONITORED BY A PA LICENSED PE AT ALL TIMES. *2018 IBC REVIEW* · 1 permit