The subs and their phones are locked. Pro shows every one, $27 a month.
Trades on this job
Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
Electrical
Electrical permit: ENERGY CONNECTION INC, under CP-2025-006236 · Electrical Permit for combo CP-2025-006236 ELECTRICAL: Install lighting, lighting controls, receptacles as per 2017 NEC. Service is existing. · 2 permits
Apr 27, 2026 to Jul 1, 2026
Fire protection & life safety
Fire suppression permit: Willetts Sprinkler Design, Inc, under CP-2025-006236 · EZ PERMIT SPRINKLER RELOCATION (NFPA 13)- For the relocation of sprinkler heads as per attached standards. Deviations from these standards require submission of construction and site plans. Relocate 65 existing sprinkler heads to accommodate new wall and ceiling layouts. · 2 permits