The subs and their phones are locked. Pro shows every one, $27 a month.
Trades on this job
Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
Plumbing
Plumbing permit: On Point Plumbing LLC, under CP-2026-005021 · - Approved plumbing work associated with an (Addition or Alteration) per EZ Permit Standard for Plumbing. · 2 permits
Sep 8, 2026 to Oct 6, 2026
Fire protection & life safety
Fire suppression permit: A & S SPRINKLER CO INC, under CP-2026-005021 · For the Relocation of Sprinkler Heads as per attached standards. Deviations from these standards require submission of construction and site plans. · 2 permits
Sep 8, 2026 to Oct 21, 2026
Electrical
Electrical permit: Joseph Irwin, under CP-2026-004675 · Install new 250 Amp MCB panel, switch over existing lighting and power to new panel. Install fire alarm per approved drawing. NEC 2020 NFPA 2019 · 2 permits
Sep 15, 2026 to Oct 21, 2026
HVAC
Mechanical permit: MATT ECKERT, under CP-2026-004675 · FOR THE INSTALLATION OF A NEW HVAC SYSTEMS, ASSOCIATED DUCT WORK, ROOFTOP UNITS, AND REGISTERS/DIFFUSERS AS PER APPROVED PLANS. SEPARATE PERMIT REQUIRED FOR ELECTRICAL, PLUMBING, FIRE SUPPRESSION. *2021 IMC* · 2 permits
Sep 15, 2026 to Oct 21, 2026
Fire protection & life safety
Fire suppression permit: Aqueduct Fire Protection Systems, LLC, under CP-2026-004675 · EZ PERMIT SPRINKLER RELOCATION (NFPA 13)- For the Relocation of Sprinkler Heads as per attached standards. Deviations from these standards require submission of construction and site plans. *CP-2026-004675* RELOCATION OF (6) SPRINKLER HEADS · 2 permits