Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
Fire protection & life safety
Fire suppression permit: JAMES W KENNEDY, under CP-2026-000239 · EZ PERMIT SPRINKLER RELOCATION (NFPA 13)- For the relocation of sprinkler heads as per attached standards. Deviations from these standards require submission of construction and site plans. Relocate 10 sprinklers for new bakery layout · 2 permits
Feb 3, 2026 to Feb 6, 2026
HVAC
Mechanical permit: WORTH AND COMPANY INC, under CP-2026-000239 · FOR THE INSTALLATION OF APPLIANCES TO BE INSTALLED IN ACCORDANCE WITH THE MANUFACTURER’S SPECIFICATIONS. FOR USE AS PREVIOUSLY APPROVED. ALL WORK TO BE DONE PER APPROVED PLANS. IF FIELD CONDITIONS VARY CONTACT DESIGN ENGINEER PRIOR TO THE START OF ANY WORK. SEPARATE PERMITS TO BE OBTAINED FOR ALL OTHER WORK. · 2 permits
Feb 3, 2026 to Mar 16, 2026
Electrical
Electrical permit: PRIME ELECTRICAL CONTRACTORS INC, under CP-2026-000239 · Installation of power, lighting and new branch circuits · 2 permits
Feb 3, 2026 to Feb 13, 2026
Plumbing
Plumbing permit: LGB MECHANICAL INC, under CP-2026-000239 · Renovate existing space with new sinks ALL WORK TO BE PERFORMED IN STRICT COMPLIANCE WITH 2018 PPC AND PLUMBING EZ STANDARD. · 2 permits