The subs and their phones are locked. Pro shows every one, $27 a month.
Trades on this job
Concrete Not named yet. The concrete sub shows up here when the shoring or post tension permit is pulled, usually months before the pour. The trades below are the permits pulled so far, often on the sales gallery or the existing site.
Fire protection & life safety
Fire suppression permit: Precision Sprinkler Services, Inc, under CP-2025-004830 · FOR INSTALLATION OF FOUR-INCH FIRE SERVICE LINE, FOUR-INCH BACKFLOW PREVENTER AND FIRE SPRINKLER SYSTEM IN ACCORDANCE WITH APPROVED PLANS, HYDRAULIC CALCULATIONS AND NFPA 13. · 2 permits
Dec 11, 2025 to Jan 5, 2026
Plumbing
Plumbing permit: GM MECHANICAL SERVICES, under CP-2025-004830 · ALTERATIONS TO EXISTING COMMERCIAL BUILDING. INTERIOR INSTALLATION OF DRAINAGE, WASTE, VENT, AND WATER SUPPLY FOR LISTED FIXTURES. ALL MATERIALS SHALL BE METALLIC TO ROOF EXTENSION. VENTING TO BE DESIGNED AND INSTALLED IN ACCORDANCE WITH SECTION 919 PHILADELPHIA SINGLE STACK VENT SYSTEM. ALL WORK TO BE INSTALLED IN STRICT COMPLIANCE WITH 2018 PPC AND APPROVED PLANS · 2 permits
Dec 11, 2025 to Mar 31, 2026
Electrical
Electrical permit: LAY BROTHERS ELECTRIC, INC, under CP-2025-004830 · Install a 600-amp main distribution panel (MDP) for the Performing Arts Center. Provide new subpanel locations, including one 225-amp subpanel serving receptacle circuits and one 225-amp subpanel serving lighting circuits. Install fire alarm system wiring and provide power for HVAC equipment at the designated locations. All work to be done according to the 2017 NEC, 2016 NFPA 72 and per approved plans. · 2 permits
Dec 11, 2025 to Jan 14, 2026
HVAC
Mechanical permit: OREILLY EDWARD B & ASSOC INC, under CP-2025-004830 · FOR THE INSTALLATION OF HVAC APPLIANCES, EQUIPMENT, DUCTWORK AND REGISTERS/DIFFUSERS PER APPROVED PLANS AND MANUFACTURER'S SPECIFICATIONS. *2018 IMC REVIEW* · 2 permits